NEW QUESTION # 15
Which of the following is a Boundary document?
- A. Programme preparation plan
- B. Risk register
- C. Benefits Map
- D. Stakeholder profiles
Answer: C
NEW QUESTION # 16
Which of following is correct about Benefits Management?
- A. Ensures programme is aware of positive and negative impact it might generate
- B. Ensures programme does right things and is aligned with strategy
- C. Is tightly aligned to transformational flow processes
- D. All of above
Answer: D
NEW QUESTION # 17
Who is accountable for approval to proceed?
- A. SRO
- B. Programme board
- C. Sponsoring Group
- D. Group of directors
Answer: A
NEW QUESTION # 18
Which of the following statements is FALSE?
- A. The SRO is likely to be a peer of the Sponsoring Group.
- B. The SRO must have enough seniority to take on accountability for the programme delivery.
- C. The SRO is appointed by the Sponsoring Group.
- D. The SRO acts as the Project Executive on all the Project Boards.
Answer: D
NEW QUESTION # 19
Which of the following defines an Emergent programme?
- A. Must do programmes often due to result of an external event and aimed to avoid negative implications
- B. Translation of political priorities into a programme to refine and deliver desired changes
- C. Programme focused on transforming the way business functions
- D. Evolved from concurrent, individual projects with need to ensure compliance to organization strategy
Answer: D
NEW QUESTION # 20
Which of the following is a KEY attribute for a Programme Manager?
- A. Change management skills
- B. Have ongoing operational responsibilities within their business area
- C. Have access to key stakeholders
- D. A good knowledge of project management approaches
Answer: D
NEW QUESTION # 21
Which of below statements are false?
- A. End of tranche review drives benefits management
- B. Benefits management identifies dependency in plans
- C. Benefits management identify risks
- D. Benefits management qualifies Blueprint
Answer: A
NEW QUESTION # 22
Which of the following is not correct about 'Leading change'?
- A. Get approval from sponsoring group
- B. Appoint right people at right time
- C. Actively engage stakeholder
- D. Create novel solutions to problems
Answer: A
NEW QUESTION # 23
Which of following best defines Outcomes?
- A. Completed set of project outputs
- B. New operational state achieved after transition of capability in live operations
- C. Deliverable of a project
- D. Measurable improvement resulting from outcomes perceived as advantage
Answer: B
NEW QUESTION # 24
Which of following is a key attribute for a SRO?
- A. Should represent a relevant business area
- B. Have access to and credibility with key stakeholders
- C. Have ongoing operational responsibilities
- D. Good knowledge of project management approaches
Answer: B
NEW QUESTION # 25
Which of the following is kind of a vision led programme?
- A. Programme evolved from concurrent, individual projects with need to ensure compliance to organization strategy
- B. Must do programmes due to change in legislation
- C. Public programme started to fulfil electoral promises
- D. Programme focused on bringing organization in tune with laws of the country of operations
Answer: C
NEW QUESTION # 26
Select the best option defined by following sentence: 'Action of carrying out the coordinated organization, direction and implementation of dossier of projects and transformation activities to achieve desired outcomes'
- A. Organizational Management
- B. Programme Management
- C. Project Management
- D. Portfolio Management
Answer: B
NEW QUESTION # 27
Which of the following is an activity in Defining a Programme?
- A. Manage transition
- B. Produce the Programme Brief
- C. Align the projects with benefits realization
- D. Design the Projects Dossier
Answer: D
NEW QUESTION # 28
Who is accountable for confirming programme closure?
- A. SRO
- B. BCM
- C. Sponsoring group
- D. Programme Manager
Answer: A
NEW QUESTION # 29
Which principle ensures creating a 'Vision'?
- A. Adding value
- B. Leading Change
- C. Envisioning and communicating a better future
- D. Focusing on benefits and threats to them
Answer: C
NEW QUESTION # 30
Programme needs to create a working environment that is both robust and flexible enough to be able to cope with frequent and sometimes radical changes of boundary. Which programme management principle suggests this?
- A. Leading change
- B. Envisioning and communicating better future
- C. Adding value
- D. Remaining aligned with corporate strategy
Answer: D
NEW QUESTION # 31
Which of the following is not an Input to delivering the capability?
- A. Project outputs
- B. Project dossier
- C. Business Case
- D. Blueprint
Answer: A
NEW QUESTION # 32
Who has the responsibility for monitoring the progress of benefits realization against the plan?
- A. Programme Manager
- B. Programme Office
- C. Business Change Manager
- D. Senior Responsible Owner
Answer: C
NEW QUESTION # 33
Which of following is not a principal control for managing the tranches?
- A. Business Case
- B. Business Case
- C. Benefit Review
- D. Dependency management
Answer: D